How Long Does it Take to Install Commercial Solar Panels

How Long Does it Take to Install Commercial Solar Panels?

In a climate like Australia, commercial solar power systems are effective and productive. Therefore, more people are choosing solar as the principal energy provider.

Making such a change can be challenging, and one of the main questions many have is to know how long it would take to install the complete solar system. This article will help you understand the steps to install commercial solar systems and give you an idea of the time expected to complete it.

Of course, the exact time it takes to install commercial solar panels will vary depending on the sizes, the complexity of the local permit and requirements, and the company you choose. You should estimate a period between a few weeks to a few months on average. Let’s walk you through the solar installation process to give you a precise idea of your asset.

Choosing the Right Solar Installer

The choice of your solar installer will be the fastest and most significant step on your solar journey. Make sure you choose a reliable company; do not pick the cheapest but the one that provides quality in terms of services, installation and maintenance.

Take time to do some research and get different quotes from solar companies. Go online to find positive reviews and check their experience. The solar company must have a NABCEP-certified installer. 

Determine the Site Assessments and System Design

This step will take your solar installer about one week. The company will perform a site assessment, checking the suitability of your roof to support a solar installation.

An experienced worker will review your roof condition, shading, size and direction. The person must tell you if your roof needs any upgrades to be compatible with your future solar installation.

Then, an engineer will design your solar system, considering all the specifics of your building and roof.

Apply for a Building and Solar Permit

Getting your permit will be the longer step of the process, which is estimated between two to seven weeks, depending on the types of tickets needed and the operations of your municipality. That step must be done before you start your installation.

Ordering Equipment and Scheduling Installation

Once you get your permits, your solar company will initiate the installation. These steps will take around one to four weeks. Some companies already have the equipment in stock; others will need to order it, which will take longer. Then, you must schedule with your operator the installation.

You may also like: Why Did Chris and Alene Leave Dr Seuss Baking Challenge

Installation

The actual installation of your solar system is actually the fastest part. It can take only six hours to three days to get all equipment in place. Well-trained workers will come and work; if you have a complex design, it will take longer, but it usually takes one day for the team to complete their task.

City Inspection

To get your installation functioning, a local inspector will come to your home to ensure the safety of your installation. Specific requirements expected will be checked in a few hours.

Utility Interconnection and Permission to Operate

The utility company will permit you to use your solar installation. That step takes two to six weeks, depending on the company’s reactivity. They must visit your property and install a new electrical meter while checking quickly that all is in order. Finally, you will get the last stamp of approval and can enjoy your solar electricity!

To summarise, you will need between two months to six months to install and be able to use a commercial solar system! This timeline will vary, taking into account different unpredictable factors.